DETAILED QUOTATION FOR RENOVATING UTANGE ORPHANAGE

Quotation Date: July 23, 2024

Project Location: Utange, Mombasa

Total Estimated Amount: Ksh. 470,150

Quotation Breakdown for Renovating Utange Orphanage

Roofing (Kshs. 107,340.00)

ItemQuantityAmount Per ItemEstimated Cost (Ksh)
Iron Sheets 3mts3Ksh. 1,400Ksh. 1,800
Roofing Nails5Ksh. 200Ksh. 1,000
Nail 415Ksh. 200Ksh. 3,000
Nail 35Ksh. 300Ksh. 1,500
Mbao 1*2240Ksh. 38Ksh. 9,120
Mbao 3*2240Ksh. 40Ksh. 9,600
Mbao 2*2180Ksh. 19Ksh. 3,420
Fisher Board1Ksh. 20,000Ksh. 20,000
Labour1Ksh. 20,000Ksh. 20,000

Wall/Plastering (Kshs. 41,800.00)

ItemQuantityAmount Per ItemEstimated Cost (Ksh)
Cement10Ksh. 680Ksh. 6,800
Sand1Ksh. 25,000Ksh. 25,000
Labour1Ksh. 25,000Ksh. 25,000

Painting (Kshs. 102,800.00)

ItemQuantityAmount Per ItemEstimated Cost (Ksh)
Crownmat 20L3Ksh. 4,200Ksh. 12,600
Silk Paint2Ksh. 12,500Ksh. 25,000
Wall Care3Ksh. 1,500Ksh. 4,500
Weather Guard Paint2Ksh. 12,500Ksh. 25,000
Weather Guard 4L1Ksh. 30,000Ksh. 30,000
Labour1Ksh. 30,000Ksh. 30,000

Tiling (Kshs. 194,780.00)

ItemQuantityAmount Per ItemEstimated Cost (Ksh)
Tiles86Ksh. 1,430Ksh. 122,980
Cement10Ksh. 680Ksh. 6,800
Grouting4Ksh. 300Ksh. 1,200
Labour1Ksh. 25,000Ksh. 25,000

Kitchen Floor (Kshs. 9,440.00)

ItemQuantityAmount Per ItemEstimated Cost (Ksh)
Cement8Ksh. 680Ksh. 5,440
Labour1Ksh. 4,000Ksh. 4,000

General Expenditure (Kshs. 14,000.00)

ItemQuantityAmount Per ItemEstimated Cost (Ksh)
Fuel To The Sight14Ksh. 1,000Ksh. 14,000