Detailed Quotation for Renovating Utange Orphanage

Quotation Date: July 23, 2024

Project Location: Utange, Mombasa

Total Estimated Amount:Ksh. 470,160

Quotation Breakdown for Renovating Utange Orphanage

Roofing Quantity Amount Per Item Estimated Cost (Ksh)
Iron Sheets 3mts 37 1,400.00 51,800.00
Roofing Nails 5 300.00 1,500.00
Nail 4" 15 200.00 3,000.00
Nail 3" 4 200.00 800.00
Mbao 4*2 240 38.00 9,120.00
Mbao 3*2 300 29.00 8,700.00
Mbao 2*2 180 19.00 3,420.00
Fisher Board 180 50.00 9,000.00
Labour 1 20,000.00 20,000.00
Total Estimated Cost 107,340.00
Wall/Plastering Quantity Amount Per Item Estimated Cost (Ksh)
Cement 10 680.00 6,800.00
Sand 1 25,000.00 25,000.00
Labour 1 25,000.00 25,000.00
Total Estimated Cost 41,800.00
Painting Quantity Amount Per Item Estimated Cost (Ksh)
Covermat 20Lt 3 4,200.00 12,600.00
Silk Paint 2 12,500.00 25,000.00
Wall Care 13 1,500.00 19,500.00
Weather Guard Paint 1 12,500.00 12,500.00
Weather Guard 4Lt 1 3,200.00 3,200.00
Labour 1 30,000.00 30,000.00
Total Estimated Cost 102,800.00
Tiling Quantity Amount Per Item Estimated Cost (Ksh)
Tiles 86 1,430.00 122,980.00
Cement 45 680.00 30,600.00
Grouting 4 300.00 1,200.00
Labour 1 40,000.00 40,000.00
Total Estimated Cost 194,780.00
Kitchen Floor Quantity Amount Per Item Estimated Cost (Ksh)
Cement 8 680.00 5,440.00
Labour 1 4,000.00 4,000.00
Total Estimated Cost 9,440.00
General Expenditure Quantity Amount Per Item Estimated Cost (Ksh)
Fuel To The Sight 14 1000.00 14,000.00
Total Estimated Cost 14,000.00
Back to Utange Orphanage