Detailed Quotation for Rabai Mosque, Imam's Quarters and Madrassa Project

Quotation Date: October 23, 2024

Project Location: Ganga, Rabai

Total Estimated Amount: Ksh. 396,900

Quotation Breakdown for Imam Quarters Repair and Restoration

Wall/Plastering Quantity Amount Per Item Estimated Cost (Ksh)
Cement 53 720.00 37,100.00
Stones 1500 60.00 90,000.00
Sand 7Tonnes 1 12,000.00 12,000.00
Skim Coat 16 1,500.00 24,000.00
Labour 35,000.00 35,000.00
Total Estimated Cost 198,100.00
Painting Quantity Amount Per Item Estimated Cost (Ksh)
Covermat 1 4,300.00 4,300.00
Silk Paint 1 12,500.00 12,500.00
Weather Guard 1 12,500.00 12,500.00
Sandpaper 5 100.00 500.00
Labour 15,000.00 15,000.00
Total Estimated Cost 44,800.00
Windows Quantity Amount Per Item Estimated Cost (Ksh)
Windows 4 12,000.00 48,000.00
Windows small 1 6,000.00 6,000.00
Total Estimated Cost 54,000.00
Electrical Quantity Amount Per Item Estimated Cost (Ksh)
Materials 35,000.00 35,000.00
Labour 1 15,000.00 15,000.00
Total Estimated Cost 50,000.00
Plumbing Quantity Amount Per Item Estimated Cost (Ksh)
Materials 35,000.00 35,000.00
Labour 1 15,000.00 15,000.00
Total Estimated Cost 50,000.00

Additional Notes

This quotation is based on a preliminary assessment and may change after commencement of work. Prove of payment and receipt will also be provided to enhance transparency