Detailed Quotation for Renovating Utange Orphanage
Quotation Date: July 23, 2024
Project Location: Utange, Mombasa
Total Estimated Amount:Ksh. 470,160
Quotation Breakdown for Renovating Utange Orphanage
Roofing |
Quantity |
Amount Per Item |
Estimated Cost (Ksh) |
Iron Sheets 3mts |
37 |
1,400.00 |
51,800.00 |
Roofing Nails |
5 |
300.00 |
1,500.00 |
Nail 4" |
15 |
200.00 |
3,000.00 |
Nail 3" |
4 |
200.00 |
800.00 |
Mbao 4*2 |
240 |
38.00 |
9,120.00 |
Mbao 3*2 |
300 |
29.00 |
8,700.00 |
Mbao 2*2 |
180 |
19.00 |
3,420.00 |
Fisher Board |
180 |
50.00 |
9,000.00 |
Labour |
1 |
20,000.00 |
20,000.00 |
Total Estimated Cost |
107,340.00 |
Wall/Plastering |
Quantity |
Amount Per Item |
Estimated Cost (Ksh) |
Cement |
10 |
680.00 |
6,800.00 |
Sand |
1 |
25,000.00 |
25,000.00 |
Labour |
1 |
25,000.00 |
25,000.00 |
Total Estimated Cost |
41,800.00 |
Painting |
Quantity |
Amount Per Item |
Estimated Cost (Ksh) |
Covermat 20Lt |
3 |
4,200.00 |
12,600.00 |
Silk Paint |
2 |
12,500.00 |
25,000.00 |
Wall Care |
13 |
1,500.00 |
19,500.00 |
Weather Guard Paint |
1 |
12,500.00 |
12,500.00 |
Weather Guard 4Lt |
1 |
3,200.00 |
3,200.00 |
Labour |
1 |
30,000.00 |
30,000.00 |
Total Estimated Cost |
102,800.00 |
Tiling |
Quantity |
Amount Per Item |
Estimated Cost (Ksh) |
Tiles |
86 |
1,430.00 |
122,980.00 |
Cement |
45 |
680.00 |
30,600.00 |
Grouting |
4 |
300.00 |
1,200.00 |
Labour |
1 |
40,000.00 |
40,000.00 |
Total Estimated Cost |
194,780.00 |
Kitchen Floor |
Quantity |
Amount Per Item |
Estimated Cost (Ksh) |
Cement |
8 |
680.00 |
5,440.00 |
Labour |
1 |
4,000.00 |
4,000.00 |
Total Estimated Cost |
9,440.00 |
General Expenditure |
Quantity |
Amount Per Item |
Estimated Cost (Ksh) |
Fuel To The Sight |
14 |
1000.00 |
14,000.00 |
Total Estimated Cost |
14,000.00 |
Additional Notes
This quotation is based on a preliminary assessment and may change after commencement of work. Prove of payment and receipt will also be provided to enhance transparency
Back to Rabai Project page