Detailed Quotation for Renovating Utange Orphanage

Quotation Date: July 23, 2024

Project Location: Utange, Mombasa

Total Estimated Amount:Ksh. 470,160

Quotation Breakdown for Renovating Utange Orphanage

Roofing Quantity Amount Per Item Estimated Cost (Ksh)
Iron Sheets 3mts 37 1,400.00 51,800.00
Roofing Nails 5 300.00 1,500.00
Nail 4" 15 200.00 3,000.00
Nail 3" 4 200.00 800.00
Mbao 4*2 240 38.00 9,120.00
Mbao 3*2 300 29.00 8,700.00
Mbao 2*2 180 19.00 3,420.00
Fisher Board 180 50.00 9,000.00
Labour 1 20,000.00 20,000.00
Total Estimated Cost 107,340.00
Wall/Plastering Quantity Amount Per Item Estimated Cost (Ksh)
Cement 10 680.00 6,800.00
Sand 1 25,000.00 25,000.00
Labour 1 25,000.00 25,000.00
Total Estimated Cost 41,800.00
Painting Quantity Amount Per Item Estimated Cost (Ksh)
Covermat 20Lt 3 4,200.00 12,600.00
Silk Paint 2 12,500.00 25,000.00
Wall Care 13 1,500.00 19,500.00
Weather Guard Paint 1 12,500.00 12,500.00
Weather Guard 4Lt 1 3,200.00 3,200.00
Labour 1 30,000.00 30,000.00
Total Estimated Cost 102,800.00
Tiling Quantity Amount Per Item Estimated Cost (Ksh)
Tiles 86 1,430.00 122,980.00
Cement 45 680.00 30,600.00
Grouting 4 300.00 1,200.00
Labour 1 40,000.00 40,000.00
Total Estimated Cost 194,780.00
Kitchen Floor Quantity Amount Per Item Estimated Cost (Ksh)
Cement 8 680.00 5,440.00
Labour 1 4,000.00 4,000.00
Total Estimated Cost 9,440.00
General Expenditure Quantity Amount Per Item Estimated Cost (Ksh)
Fuel To The Sight 14 1000.00 14,000.00
Total Estimated Cost 14,000.00

Additional Notes

This quotation is based on a preliminary assessment and may change after commencement of work. Prove of payment and receipt will also be provided to enhance transparency